全国免费咨询热线
4001-666-001
我的位置:部门首页>案例列表>案例详情

CONTRACT FOR PROCUREMENT OF HAMMER MILL FOR SHENDONG BAODE POWER PLANT, 2X135MW UNIT PROJECT

更新时间:2016/1/6 点击次数:1807 作者:admin


Decision on Dismissal

By

China International Economic and Trade Arbitration Commission

CLAIMANT: Shanghai Mindac Machinery Equipment Co., Ltd.

ADDRESS: Unit A,23 FL.,Majesty Building,No.l38 Pudong Avenue

Pudong District, Shanghai, P.R.C.

LEGAL REPRESENTATIVE: Ms.FuMinyan

ARBITRATION AGENTS: Ms. Mao Shujing & Mr. Qiao Yanchun,

Attorneys at Law 

RESPONDENT: AUBEMA Crushing Technology GmbH

(Fonner Name: AUBEMA MASCHINENFABRIK GMBH) 

ADDRESS:Koelner Strasse 94, D-51702, Bergneustadt, Gennany ARBITRAI ION AGENT: Mr. Tim Meng, Attorney at Law


April 18,2008

Beijing



Decision on Dismissal


(2008) CIETAC Award No. 0185

The China International Economic and Trade Arbitration Commission (hereinafter referred to as the CIETAC) accepted a reference of a 

dispute arising out of the CONTRACT FOR PROCUREMENT OF HAMMER MILL FOR SHENDONG BAODE POWER PLANT, 

2X135MW UNIT PROJECT (CONTRACT NO. MINDACAUB-BAODE-2004-247, hereinafter referred to as theContract)signed by and between the Claimant Shanghai Mindac Machinery Equipment Co.,Ltd. (hereinafter referred to as the Claimant”)

and the Respondent AUBEMA Crushing Technology GmbH (Former Name: AUBEMA MASCHINENFABRIK GMBH, hereinafter referred

 to the the Respondent) on 27 September 2004.

The dispute was referred to the CIETAC pursuant to Clause 24Resolution of Disputesof the Contract. It states as follows:

24.1 All disputes arising from the execution of or in connection with the Contract shall be settled through friendly consultation by both parties.

 In case no settlement can be reached within sixty (60) days ofcommencement of such consultation, the dispute shall be submitted for arbitration.

24.2 Arbitration organization shall be China International Economic and Trade Arbitration Commission (CIETAC). The Commissioncomprises

 two person chose by both parties respectively and one personnegotiated by both parties.

······

The CIETAC cognizance of the dispute for arbitration based onthearbitration clause incorporated inthe Contract, and the writtenarbitration 

application filed by the Claimant on 29 April 2007. TheCIETAC numberof the case is M20070279 to which the ArbitrationRulesof the China

 International Economic and Trade ArbitrationCommission effective as from 1 May 2005 (hereinafter referred to as the CIETAC Arbitration

 Rules) applies.

A NoticeofArbitration was sent to the Claimant and the Respondent respectively on 4 June 2007 by the Secretariat of the CIETAC (hereinafter

 referred to as he Secretarial). Attached to the Notice of Arbitration to the Claimant were the Panel of Arbitrators and CIETAC Arbitration 

Rules and to the Respondent were the Application for Arbitration submitted bythe Claimant,the Panel of Arbitrators and the CIETAC Arbitration

 Rules.

On 23 October 2007, an Arbitration Tribunal was formed consisting of Mr. Shen Sibao, the Presiding Arbitrator appointed by the Chairman 

of the CIETAC under the CIETAG Arbitration Rules as the parties failed to jointlappoint or jointly entrust the Chairmanto appointedbypresiding

 arbitrator within the time limit, Mr. Wan Meng, the Arbitrator appointed by the Claimant, and Ms. Yan Siyi, the Arbitrator appointed by the 

Respondent. A Notice on the Formation of Arbitral Tribunal was sent to the Claimant and the Respondent respectively on the same day.

On 28 November 2007, the Respondent submitted the Statement ofCounterclaims and attached evidence. The Secretariat transmitted these 

documents to the Claimant.

On 7 January 2008, the Claimant requested for extension of the timelimit for submitting defense against counterclaims. The Secretariat transmitted to the Respondent on the next day.

On 8January 2008, the Respondent agreed to the Claimants aboverequest in writing. The Tribunal decided to extend the time limit for theClaimant

submission of defense against counterclaims to 20 February 2008 accordingly.

The Tribunal, in consultation with the Secretariat, decided to hold an oral hearing on 1-3 April 2008. The Secretariat sent the Notice on Oral Hearing t0 the parties on 23 January 2008.

On 19 February 2008, the Claimant submitted the Statement of Defense. The Secretariat transmitted it to the Respondent.

On 24 March 2008, the Respondent submitted the supplemental evidence. The Secretariat transmitted it to the Claimant.

On 27 March 2008, the Claimant submitted supplemental evidence.The Secretariat transmitted the evidence to the Respondent on the same day.

On 1 April 2008, the Secretariat notified the parties the oral hearing

scheduled on 1-3 April 2008 was cancelled since parties had reachedsettlement.

During the arbitration procedure, the Claimant submitted the Application for Withdrawing (Re: Arbitration Case No. M20G70279) dated 7 

April 2008, which is as follows:

The captioned case was brought to arbitration on April 29, 2007,

and was accepted by your good Commission on June 4, 2007. Finally, the

parties reached a settlement. We hereby represent MINDAC to withdraw the captioned application to close the procedure in your goodCommission.

TheRespondent submitted its application for withdrawal (Re:CIETAC Cases No.M20070278, M20070279, M20070280 & M2007028l) on10 April 

2008, stating that:

TheClaimant and Respondent signed a Settlement Agreement on March 31, 2008. More than one week has passed since then, and the parties show

 no signs of retrograde movement.

As such, in accordance with Article 41 of the applied Arbitration

Rulesin those cases and furthertoourlastrequestsweherebyrequesta

withdrawal of the claims made by us in the Statement of Counter-claims in these cases listed in the title.”

It is stipulated in Article 41.2 of the CIETAC Arbitration Rules that“where a case is to be dismissed before the formation of the arbitraltribunal, the

decision shall be made by the Secretary-General of the CIETAC. Where the case is to be dismissed after the formation of arbitral tribunal, the decision shall be made by the arbitral tribunal

Therefore, according to the Claimants and the Respondents request for withdrawal of this case, the Tribunal has made the following decisions:

1、that the captioned No. M20070279 Arbitration Case on Disputes

Arising out of the CONTRACT FOR PROCUREMENT OF HAMMER MILL FOR SHENNDONG BAODE POWER PLANT, 2X135MW UNIT

PROJECT between the Claimant and the Respondent is dismissed;

2that the arbitration fee for claims of this case is RMB 26,393which shall be borne by the Claimant, since the Claimant has remitted RMB 

42,786 as the prepaid arbitration fee, the CIETAC is to refund the Claimant RMB 16,393 after subtracting the arbitration fee from theprepaid 

amount; the arbitration fee for counterclaims of this case is USD 1,404, since the Respondent has remitted USD 2,807 as the prepaid arbitration 

fee, the CIETAC is to refund the Respondent USD 1,403 after subtracting the arbitration fee from the prepaid amount.



Presiding  Arbitrator:

Arbitrator:

Arbitrator:

April 18, 2008 at Beijing