全国免费咨询热线
4001-666-001
我的位置:部门首页>案例列表>案例详情

CONTRACT FOR PROCUREMENT OF HAMMER MILL FOR CHONGQING SHUIJIANG POWER CO., LTD, 1 X 30MW UNIT PROJECT

更新时间:2016/1/7 点击次数:1713 作者:admin

Decision on Dismissal

By

China International Economic and Trade

Arbitration Commission


CLAIMANT: Shanhai Mmdac Machinery Equipment Co., Ltd. 

ADDRESS: Unit A, 23 FL.5Majesty Building, No.138 Pudong Avenue, Pudong Distr          ict, Shaaghai, P.R.C.

LEGAL REPRESENTATIVE: Ms.Fu Minyan

ARBITRATION AGENTS: Ms. Mao Shujing & Mr. Qiao Yanchun,Attorneys at Law

RESPONDENT: AUBE3VIA Crushing Technology GmbH

(Former Name: AUBEMA MASCHINENFABRIK GMBH)

ADDRESS: Koelner Strasse 94, D-51702,  Bergneustadt,Germany ARBITRATION AGENT: Mr. Tim Meng,Attorney at Law

April 18,2008

Beijing


Decision on Dismissal


(2008) CIETAC Award No. 0186


The China International Economic and Trade Arbitration Commission (hereinafter referred to as “the CIETAC”) accepted a reference of a dispute

 arising out of the CONTRACT FOR PROCUREMENT OF HAMMER MILL FOR CHONGQING SHUIJIANG POWER CO., LTD, 1 X 30MW UNIT

 PROJECT (CONTRACT NO.: MINDACAUB-SHUIJLANG-2004-239, hereinafter referred to as "the Contract”)signed by and between the Claimant Shanghai Mndac Machinery Equipment Co., Ltd. (hereinafter referred to as “the Claimant”)and  the  Respondent  AUBEMA Crashing  Technology  GmbH  (Former  Name:  AUBEMA  MASCHINENFABRIK  GMBH, hereinafter referred to the “the Respondent”)on 27 September 2004.

The dispute was referred to the CIETAC pursuant to Clause 24 "Resolution 

of Disputes” of the Contract. It states as follows:

"24.1 All disputes arising from the execution of or in connection with the Contract shall be settled through friendly consultation by both parties. In case

 no settlement can be reached within sixty (60) days of commencement of such consultation, the dispute shall be submitted for arbitration.

24.2 Arbitration organization shall be China International Economic and Trade Arbitration Commission (CIETAC). The Commission comprises two person

 chose by both parties respectively and one person negotiated by both parties.

The CIETAC took cognizance of the dispute for arbitration based on the arbitration clause incorporated in the Contract, and the written arbitration

 application filed by the Claimant on 29 April 2007. The CIETAC number of the case is M20070280 to which the Arbitration Rules of the China 

International Economic and Trade Arbitration Commission effective as from 1 May 2005 (hereinafter referred to as "the CIETAC Arbitration Rules")applies.


A Notice of Arbitration was sent to the Claimant and the Respondent respectively on 4 June 2007by the Secretariat of the CIETAC (hereinafter 

referred to as "the Secretariat"). Attached to the Notice of Arbitration to the Claimant were the Panel of Arbitrators and CIETAC Arbitration Rules, and to the 

Respondent were the Application for Arbitration submitted by the Claimaint, the Panel of Arbitrators and the CIETAC Arbitration Rules.


On 23 October 2007, an Arbitration Tribunal was formed consisting of Mr. Shen Sibao, the Presiding Arbitrator appointed by the Chairman of the 

CIETAC under the CIETAC Arbitration Rules as the parties failed to jointly appoint or jointly entrust the Chairman to appoint the presiding 

arbitrator within thetime limit, Mr. Wan Meng, the Arbitrator appointed by the Claimant,and Ms. YanSiyi, the Arbitrator appointed by the Respondent.

A Notice on the Formation of Arbitral Tribunal was sent to the Claimant and the Respondent respectively on the same day.

On 13 November 2007, the Respondent submitted the Request for Extension for Submitting Counterclaim. On 16 November 2007, the Secretariat sent 

the notice on the Tribunal's decision to extend the time limit for the Respondent’s submission of defense and/or counterclaims to 17 December 2007.


On 6 December 2007, the Respondent submitted the Statement of Counterclaims and attached evidence. The Secretariat transmitted these documents to 

the Claimant.

The Tribunal, in consultation with the Secretariat, decided to hold an oral hearing on 1-3 April 2008. The Secretariat sent the Notice on Oral Hearing to the parties on 23 January 2008.

On 23 January 2008, the Claimant requested for extension of the time limit for submitting defense against counterclaims. The Secretariat transmitted 

the request to the Respondent on the next day.

On 29 January 2008, the Respondent agreed to the Claimant's above request in writing. The Tribunal decided to extend the time limit for the 

Claimant’s submission of defense against counterclaims to 20 March 2008 accordingly.

On 20 March 2008, the Claimant submitted the Statement of Defense. The Respondent submitted supplementary evidence on the next day. On 25 March 

2008, the Secretariat made exchange of the above documents between the parties.

On 27 March 2008, the Claimant submitted supplementary evidence. The Secretariat transmitted the evidence to the Respondent on the same day.

On 1 April 2008, the Secretariat notified the parties the oral hearing scheduled on 1-3  April  2008  was  cancelled  since  the  parties  had 

reached settlement.

During the arbitration procedure, the Claimant submitted the Application for Withdrawing (Re: Arbitration Case No. M20070280) dated 7 April 2008, 

which is as follows:

“The captioned case was brought to arbitration on April 29, 2007, and was accepted by your good Commission on June 4, 2007. Finally, the parties

 reached a settlement. We hereby represent MINDAC to withdraw the captioned application to close the procedure in your good Commission.”

The Respondent submitted its application for withdrawal (Re: CIETAC Cases No. M20070278, M20070279, M20070280 & M20070281) on 10 April 2008, stating

 that:

"The Claimant and Respondent signed a Settlement Agreement on March 31, 2008. More than one week has passed since then, and the parties show no

 signs of retrograde movement.

As such,in accordance with Article 41 of the applied Arbitration Rules’in those cases and farther to our last requests, we hereby request a 

withdrawal of the claims made by us in the Statement of Counterclaims in these cases   listed in the title."

It is stipulated in Article 41.2 of the CIETAC Arbitration Rules that “where a case is to be dismissed before the formation of the arbitral 

tribunal, the decision shall be made by the Secretary-General  of  the  CIETAC.  Where  the case is to be dismissed after the formation of arbitral tribunal, the decision shall be made by the arbitral tribunal" Therefore, according

 to the Claimant's and the Respondent's request for withdrawal of this case, the Tribunal has made the following decisions:

1、that  the  captioned  No.  M20070280  Arbitration  Case  on  Disputes  Arising out of the CONTRACT FOR PROCUREMENT OF HAMMER MILL FOR CHONGQING SHUIJIANG POWER CO., LTD, 1X30MW UNIT PROJECT between the Claimant and

 the Respondent is dismissed; 

2、that the arbitration fee for claims of this case is RMB25,000 which  shall be borne by the Claimant, since the Claimant has remitted RMB 40,000 as the prepaid arbitration fee, the CIETAC is to refund the Claimant

 RMB 15,000 after subtracting the arbitration fee from the prepaid amount; the arbitration fee for counterclaims of this case is USD 637, since 

the Respondent has remitted USD 1,274 as the prepaid arbitration fee, the CIETAC is to refund theRespondent USD 637 after  subtracting the 

arbitration fee from the prepaid amount.



Presiding  Arbitrator:

Arbitrator:

Arbitrator:

April 18, 2008 at Beijing